QuestionQ220

VerifiedSecure Software Lifecycle Management

Phase 2 of DITSCAP C&A is called Verification. The objective of this phase is to obtain a fully integrated system for certification testing and accreditation. What are this phase’s process activities? Each correct answer represents a complete solution. Choose all that apply.

Choose four
Explanation

DITSCAP Verification activities consist of refining the SSAA as the system evolves, developing and integrating the system, performing certification analysis to determine readiness for validation, and assessing the analysis results. Registration initiates the DITSCAP process during Phase 1, Definition, rather than Phase 2.