QuestionQ202

VerifiedSecure Software Lifecycle Management

A portion of the project involves hardware work. As the project manager, you have decided to hire a company to handle all hardware work for the project. Which type of risk response does this represent?

Explanation

Risk transference shifts responsibility for a risk and its potential impact to a third party, such as a contractor hired to perform the hardware work.