VerifiedSecure Software ConceptsYou are the project manager for a construction project. The project requires casting a column in a very narrow space. Because space is limited, casting it is highly dangerous. High technical skill is required to cast that column. You decide to hire a local expert team to cast it. Which type of risk response are you following?