QuestionQ127
VerifiedSecure Software Lifecycle ManagementAdrian is the project manager for the NHP Project. Her project includes several work packages involving electrical wiring. Rather than managing the risk internally, she has chosen to hire a vendor to complete all work packages involving electrical wiring. By transferring the internal risk to a licensed electrician, Adrian feels more comfortable that the project team will be safe. What type of risk response has Adrian used in this example?