QuestionQ121

Secure Software Lifecycle Management

Which of the following processes does the Project Risk Management knowledge area focus on? Each correct answer represents a complete solution. Choose all that apply.

Choose three
  • A Risk Monitoring and Control
  • B Risk Management Planning
  • C Quantitative Risk Analysis
  • D Potential Risk Monitoring
Explanation

Project Risk Management includes the processes of Risk Management Planning, Quantitative Risk Analysis, and Risk Monitoring and Control. Risk monitoring addresses identified and residual risks, while “Potential Risk Monitoring” is not a defined PMI project-risk-management process.