VerifiedSystems Lifecycle ManagementYou are the project manager for a large construction project. Within the project, you are working with several vendors to complete different construction phases.
Your client has asked you to arrange a change to some materials that a vendor is scheduled to install next week. According to the change management plan, which subsystem will need to manage this change request?