QuestionQ75

Systems Lifecycle Management

You are the project manager for a large construction project. Within the project, you are working with several vendors to complete different construction phases.

Your client has asked you to arrange a change to some materials that a vendor is scheduled to install next week. According to the change management plan, which subsystem will need to manage this change request?

  • A Cost
  • B Resources
  • C Contract
  • D Schedule
Explanation

A change to materials that a vendor must install changes vendor deliverables and may alter contractual specifications, price, or obligations. Such a change is managed through the contract subsystem.