QuestionQ75
Systems Lifecycle ManagementYou are the project manager for a large construction project. Within the project, you are working with several vendors to complete different construction phases.
Your client has asked you to arrange a change to some materials that a vendor is scheduled to install next week. According to the change management plan, which subsystem will need to manage this change request?
- A Cost
- B Resources
- C Contract
- D Schedule
Community Discussion