QuestionQ46

VerifiedSystems Lifecycle Management

Which contract type is described by the following statement: “This contract type gives the contractor no incentive to control costs and is therefore rarely used.”

Explanation

A cost-plus-percentage-of-cost contract pays the contractor a percentage of the actual cost as its fee. Higher costs therefore produce a higher fee, so the contractor has no financial incentive to control costs.