You are the project manager for your organization’s HJK project. You and the project team have developed risk responses for many project risk events. A teaming agreement is an example of which risk response?

Explanation

A teaming agreement divides responsibility for managing a risk among collaborating parties. This distributes the potential impact and ownership of the risk, which is risk sharing.