QuestionQ24

Risk Management

You are the project manager for your organization's HJK Project. You and the project team have developed risk responses for many of the project’s risk events. Where should the proposed responses and current status of all identified risks be documented?

  • A Risk management plan
  • B Lessons learned documentation
  • C Risk register
  • D Stakeholder management strategy
Explanation

A risk register records identified project risks along with their planned response actions and current status throughout the project.