QuestionQ24

VerifiedRisk Management

You are the project manager for your organization's HJK Project. You and the project team have developed risk responses for many of the project’s risk events. Where should the proposed responses and current status of all identified risks be documented?

Explanation

A risk register records identified project risks along with their planned response actions and current status throughout the project.