VerifiedRisk Management

Tomas is the project manager for the QWS Project and worries that the project stakeholders will frequently seek changes to the project scope. His concern is based on the project's many open issues and on how resolving those issues could result in further project changes. Which document are Tomas and the stakeholders working on in this scenario?

Explanation

An issue log tracks current project issues, including their status, ownership, actions, and resolution. Because the open issues are being addressed with stakeholders and their resolutions may drive scope changes, the relevant document is the issue log.