QuestionQ177

VerifiedRisk Management

Mark is the project manager for the NHQ project at Spartech Inc. The project contains an asset valued at $195,000 and has an exposure factor of 35 percent.

What is the project's Single Loss Expectancy?

Explanation

Single Loss Expectancy (SLE) is calculated by multiplying the asset value by the exposure factor. An asset value of $195,000 with a 35 percent exposure factor produces an SLE of $68,250.