Rachael is the project manager for a large project in her organization. A newly proposed change request will affect several areas of the project. One area affected by the project change involves work that a vendor has already completed. The vendor refuses to make the changes because it has already completed the project work it was contracted to perform. What can Rachael do in this situation?

Explanation

The contract agreement governs the vendor’s scope of work, completed obligations, change-control process, and any available remedies. A change affecting completed contracted work may require a contractual modification or other action specified in that agreement.