QuestionQ119

VerifiedLeadership and Organizational Management

You are the project manager for your company’s NGQQ Project. To help communicate project status to stakeholders, you will create a stakeholder register. Which of the following information should not be included in the stakeholder register?

Explanation

A stakeholder register contains identifying information and an assessment and classification of project stakeholders, including their requirements, expectations, and potential influence. Strategies for managing or engaging stakeholders belong in the stakeholder engagement/management plan rather than in the register.