You are serving as a project manager in your organization. As you approach the final stages of project execution and prepare for the last risk-monitoring and -controlling activities, which of the following is an output of risk monitoring and control for the project archives?

  • A Quantitative risk analysis
  • B Qualitative risk analysis
  • C Requested changes
  • D Risk audits
Explanation

Risk monitoring and control can identify a need to modify risk responses, plans, or other project elements; those needed modifications are issued as requested changes. Risk audits are a monitoring technique, and qualitative and quantitative risk analysis are distinct risk-management processes.