Diane is the project manager for the HGF Project. A risk identified and analyzed during the project planning processes is now materializing. Which individual should respond to the risk using the preplanned risk response?

Explanation

A risk owner is the individual assigned responsibility and accountability for monitoring a specific risk and carrying out its planned response when the risk occurs.