QuestionQ211

VerifiedRisk Management

You are serving as a project manager in your organization. As you approach the final stages of project execution and prepare for the final risk monitoring and controlling activities, which of the following is an output of risk monitoring and control for the project archives?

Explanation

Risk monitoring and control can identify a need to modify project work, plans, or risk responses; that need is issued as a requested change. Risk audits are a monitoring technique, and qualitative and quantitative risk analysis are distinct risk-management processes.