QuestionQ187Verified/Risk ManagementCopy linkReport a problemAsk AstroTutorSave questionProjects have seven risk responses. Which of the following is a valid response to a negative risk event?AAcceptanceBEnhanceCShareDExploitShow AnswerAnswerExplanationAcceptance is a valid response strategy for a negative risk (threat). It means acknowledging the threat and taking no proactive action beyond possible contingency planning. Enhance, share, and exploit are strategies for positive risks (opportunities).Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!