QuestionQ156

VerifiedRisk Management

Your project team has identified a project risk that requires a response. The risk is documented in the risk register, and the team has been discussing possible risk responses for the risk event. The event is unlikely to occur for several months, but its probability is high. Which one of the following is a valid response to the identified risk event?

Explanation

Corrective action is a documented action used to address an identified project condition and bring expected future performance into alignment with the project management plan. It can be used to implement an appropriate response to an identified risk.