QuestionQ13

VerifiedSecure Operations, Change Management and Disposal

Part of the change management plan specifies what should occur in the project’s change control system. Theresa, a junior project manager, asks which configuration management activities apply to scope changes. You explain that all of the following are valid configuration management activities except which one?

Explanation

Standard configuration management activities include configuration identification, configuration status accounting, and configuration verification and auditing. Configuration item costing is not a standard configuration management activity.