Which disaster recovery test involves shutting down operations at the primary site and transferring them to the recovery site in accordance with the disaster recovery plan?

Explanation

A full-interruption test halts production operations at the primary location and moves them to the recovery site, validating that the disaster recovery plan can support an actual failover.