When prioritizing improvement initiatives, which of the following should be scheduled to finish FIRST?

Explanation

Early improvement work should favor achievable initiatives that deliver business benefits, creating value quickly and building support for further improvement. Cost alone is not a sufficient prioritization criterion when expected business value is unknown or disregarded.