QuestionQ96

VerifiedThe Governance System Design Workflow

Which of the following is responsible for developing an EGIT business-case outline and its details?

Explanation

The CIO and program steering committee are responsible for developing the EGIT business-case outline and detailed business case because they lead and govern the implementation program, align it with enterprise strategy, and direct the initiative’s scope, benefits, resources, and investment decisions. COBIT’s implementation lifecycle calls for an outline business case at initiation and a detailed business case when defining the target state.