QuestionQ39

VerifiedGovernance Implementation Lifecycle

Which stakeholder group is responsible for creating or updating EGIT objectives after the first iteration of an EGIT program implementation life cycle has been completed?

Explanation

The CIO and business executives are responsible for maintaining alignment between EGIT objectives and evolving enterprise strategy, priorities, and business needs as the implementation life cycle iterates. IT management implements and manages the resulting practices, while risk, compliance, and audit provide advice, challenge, and assurance.