QuestionQ190

Information Security Risk Management

During which stage of business continuity planning is risk identification carried out?

  • A Impact analysis
  • B Stakeholder meeting
  • C Development
  • D Project planning
Explanation

Risk identification is performed during project planning so that the continuity-planning effort can be scoped and prioritized before impact analysis and development of the continuity plan.