QuestionQ61

Information Systems Acquisition, Development and Implementation

A new system-development project is behind schedule for a critical implementation deadline. Which of the following activities is the MOST important?

Explanation

User acceptance testing validates that the implemented system satisfies agreed business requirements and is fit for operational use before release. Schedule pressure should not bypass this essential business validation.