QuestionQ148

Governance and Management of IT

Because of a recent business divestiture, an organization has constrained IT resources for delivering critical projects. Reviewing the IT staffing plan against which of the following would BEST help IT management estimate resource requirements for future projects?

Explanation

Records of actual time spent on completed projects provide organization-specific historical effort data, supporting more accurate estimates of staffing and resource needs for future projects.