QuestionQ51

Benefits Realization

Which of the following is the BEST way to verify whether a pilot project succeeded?

  • A Evaluate whether the pilot project achieved planned schedule and cost.
  • B Review the metrics recorded in the IT balanced scorecard.
  • C Assess the results of the pilot project against the expected performance outcomes.
  • D Determine whether the pilot aligns with the as-is enterprise architecture (EA).
Explanation

Pilot-project success is determined by evaluating actual results against the expected performance outcomes established for the pilot. This directly measures whether the pilot achieved its intended objectives.