QuestionQ180

Risk Optimization

Which of the following would be of MOST concern in relation to the effectiveness of risk management processes?

  • A Risk management requirements are not included in performance reviews.
  • B Key risk indicators (KRIs) are not established.
  • C There is no framework to ensure effective reporting of risk events.
  • D The plans and procedures are not updated on an annual basis.
Explanation

An effective risk-management process requires a reliable framework for reporting and escalating risk events. Without it, risk events can go unidentified or uncommunicated, preventing timely assessment, response, governance oversight, and improvements to risk treatment.