To ensure security testing is integrated for large code sets in environments where completion time is critical, what form of validation should an auditor expect?

Explanation

When security testing has to cover a large code base inside a tight time window, the tests are split and run concurrently across multiple agents or environments, which is parallel testing; it shortens elapsed time without reducing coverage and fits CI/CD pipelines. Regression testing only confirms that changes did not break existing behaviour, and a full regression suite is itself what grows slow on large code sets. Full-stack unit testing and functional verification address scope and correctness, not completion time.