QuestionQ43

VerifiedConfigure Maximo Scheduler

In the Graphical Scheduling application, what data source is used to populate the resource load that is shown?

Explanation

The resource load graph in the Graphical Scheduling application is calculated from the planned labor hours recorded on work order labor assignments. These planned hours represent the estimated effort assigned to each resource, and the application aggregates them to show how loaded a resource is over the scheduling horizon.