On its Resources tab, the Scheduler Data Manager application checks whether crafts, crew types, and rotating tools are available in sufficient quantity to schedule the work contained in the schedule. The craft validation specifically tests whether the total number of planned craft hours exceeds all available craft hours across all shifts; when it does, the application raises the error "All work cannot be scheduled with the limited number of resources," which can be corrected by adjusting craft hours in the Scheduling Alternate Resources application. Equivalent load-versus-availability checks exist for crew type hours and rotating tool hours. Verifying that every crew position is staffed, that rotating tools are not assigned to other work orders, or that labor belongs to the same site as the work orders are not validations that this application performs on resources.