QuestionQ32

Work Management & Planning

Which condition would prevent a work order from being changed to a status of Canceled?

  • A Work order priority is set to 1
  • B The work order originated from a Service Request
  • C Reported work order type is emergency work
  • D Labor actuals have been reported against the work order
Explanation

In IBM Maximo Asset Management, a work order cannot be moved to CANCELED status if actual costs—such as labor actuals—have already been recorded against it. The system enforces this rule to preserve the integrity of cost and history records; once labor time or other actuals are reported, the work order is considered to have started incurring real costs and therefore can no longer simply be canceled (it would typically need to be closed instead). Priority level, originating from a Service Request, or being flagged as emergency work do not, by themselves, block the CANCEL status transition in standard Maximo configuration.