QuestionQ33

VerifiedManaging Workflow Center and Process Applications

In the Process Inspector, what state does a manual activity have when it has no precondition, or when its precondition evaluates to true?

Explanation

A manual activity is in the READY state when it is eligible to begin: either no precondition applies or its configured precondition evaluates to true. WAITING applies while eligibility conditions remain unmet, while WORKING and COMPLETED apply after the activity has started or finished.