QuestionQ43

VerifiedValidate, install, configure, and upgrade HPE SMB solutions and their components

You are deploying a server solution in a customer's data center.

How can you ensure the installation follows relevant electrical best practices?

Choose two
Explanation

Branch-circuit loading should remain at or below 80% of the circuit’s AC current rating for continuous loads. Server power demand should also be balanced across the available AC supply branch circuits to avoid overloading one circuit and to distribute the electrical load appropriately.