QuestionQ2

VerifiedSystem maintenance

You must replace a failed power supply (PS) in a VSP E590.

What is the proper procedure?

Explanation

Before replacing a VSP E590 power supply, block that power supply by using the Maintenance Utility, then perform the replacement. Blocking records the component’s maintenance state and permits its safe service; blocking the controller is not required for a power-supply replacement.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!