QuestionQ87

VerifiedIncident Response and Business Continuity

Management support and approval have been obtained to proceed with the objectives of a proposed BCP/DR project.

Which of the following should be performed next?

Explanation

A business impact analysis identifies critical business functions and determines the consequences of disruption, recovery priorities, and recovery requirements. Those results provide the basis for selecting recovery strategies and any backup site. NIST’s contingency-planning process places the business impact analysis immediately after establishing the planning policy, before recovery strategies.