Formal project closure is based on which of the following?

Explanation

Formal closure depends on verifying that deliverables satisfy the agreed acceptance criteria and obtaining formal acceptance from the appropriate customer or sponsor. PMI describes project closing as formalizing acceptance of deliverables and recommends documented acceptance once the scope of work is complete.