QuestionQ49

Managing Projects

The Executing Process Group maps to which component of the PDCS project-management cycle?

  • A C
  • B P
  • C D
  • D A
Explanation

Execution is the Do (D) component of the PDCS cycle, because it is the phase in which the planned project work is performed.