QuestionQ7
VerifiedManaging ProjectsJanet is the project manager for her company’s NHQ Project. She is nearly finished leading the project, and the development of the company’s new software has had no cost or schedule overruns. The project team has completed its work on time, and $75,000 remains in the project budget.
Janet decides to have the project team add extra features to the project scope in order to use all $75,000 of the budget, even though the customer did not specifically request the additional features. This scenario is an example of which of the following?