QuestionQ68

VerifiedManaging Projects

Which process is described by the following statement?

> “It is a process of developing an approximation of the costs of the resources needed to complete project activities.”

Explanation

Cost estimating develops an approximation of the monetary costs of the resources required to carry out project activities. Cost budgeting uses those estimates to create an authorized cost baseline, while cost control monitors and manages cost performance.