QuestionQ59

VerifiedManaging Projects

An organization has a standardized change-management plan that every project manager must follow. A project manager has collaborated with the organization's Change Control Board to approve a change in project scope. What should the standardized change-management plan require the project manager to do with the approved scope change?

Explanation

An approved scope change must be incorporated into the scope baseline and related project-management artifacts. Because the WBS decomposes and defines the approved project scope, it must be updated to represent the authorized scope change. PMI identifies the scope baseline as a component that may be updated through integrated change control.

Learn more