QuestionQ59

Managing Projects

An organization has a standardized change-management plan that every project manager must follow. A project manager has collaborated with the organization's Change Control Board to approve a change in project scope. What should the standardized change-management plan require the project manager to do with the approved scope change?

  • A Perform risk assessment on the new change.
  • B Communicate the change to the vendor.
  • C Create a cost estimate for the change.
  • D Update the WBS.
Explanation

An approved scope change must be incorporated into the scope baseline and related project-management artifacts. Because the WBS decomposes and defines the approved project scope, it must be updated to represent the authorized scope change. PMI identifies the scope baseline as a component that may be updated through integrated change control.