QuestionQ59
Managing ProjectsAn organization has a standardized change-management plan that every project manager must follow. A project manager has collaborated with the organization's Change Control Board to approve a change in project scope. What should the standardized change-management plan require the project manager to do with the approved scope change?
- A Perform risk assessment on the new change.
- B Communicate the change to the vendor.
- C Create a cost estimate for the change.
- D Update the WBS.