QuestionQ520

Managing Projects

Which of the following is not an output of the Acquire Project Team process?

  • A Resource calendars
  • B Enterprise environmental factors
  • C Project staff assignments
  • D Project management plan updates
Explanation

Acquire Project Team outputs include project staff assignments, resource calendars, and updates to the project management plan. Enterprise environmental factors are conditions internal or external to the organization that influence the project and serve as an input, rather than being produced by this process.