QuestionQ480

Managing Projects

Which of the following processes are part of the Project Scope Management knowledge area?

Each correct answer represents a complete solution. Choose all that apply.

Choose three
  • A Create Work Breakdown Structure (WBS)
  • B Verify Scope
  • C Select Sellers
  • D Control Scope
Explanation

Project Scope Management includes Create Work Breakdown Structure (WBS), Scope Verification (called Validate Scope in later PMBOK editions), and Control Scope. Selecting sellers is a procurement-management activity. PMI describes Create WBS, Scope Verification, and Scope Control as scope-management processes.