QuestionQ36

VerifiedManaging Projects

Which methodology analyzes the tasks involved in completing a specified project, particularly the time required for each task and the minimum time required to complete the entire project?

Explanation

PERT (Program Evaluation and Review Technique) analyzes project activities, their durations, and their dependencies to estimate the minimum time required to complete the project.