QuestionQ341

Managing Projects

You are the project manager for the GYG Project. A new scope change is under consideration for your project. However, you are concerned that the scope change could add costs and risks and adversely impact the project schedule. Which project management process is responsible for evaluating the complete effect of a proposed scope change on your project?

  • A Schedule change control
  • B Scope change control
  • C Integrated change control
  • D Change Control Board approval process
Explanation

Integrated change control evaluates change requests holistically across the project management plan and its interdependent baselines. It considers the effects on scope, schedule, cost, risk, and other project objectives before the change is approved, rejected, or otherwise resolved. A Change Control Board can be involved in decisions, but it is not the overarching evaluation process.