QuestionQ305

Managing Projects

You are a project manager for BlueWell Inc. and are working with team members on project risk responses. Which risk response is most likely to cause the project to use procurement processes?

  • A Mitigation
  • B Acceptance
  • C Exploiting
  • D Sharing
Explanation

Risk sharing assigns or allocates responsibility for a threat to another party, often through a contract, insurance, outsourcing arrangement, or similar agreement. Establishing such an arrangement generally uses procurement processes.