QuestionQ289
Managing ProjectsYou are the project manager for your organization’s Workstation Improvement Project. The project will replace 925 workstations with new computers for the company’s employees. Mark Jones, the sales manager, has asked to add 250 laptops to the project because his employees do not have workstations while traveling as part of the sales process. Mark insists that his department can pay the cost of the laptops.
All of the following components will be affected by this change request except which one?
- A There will be a need for additional time to install the laptops.
- B There will be a need for an additional project scope statement because of the change request.
- C There will be a need for additional procurement management processes.
- D There will be a need for additional risk analysis for the laptops.
Community Discussion