QuestionQ287

Managing Projects

You are an IT project manager analyzing activity sequences, durations, resource requirements, and schedule constraints in order to develop the project schedule. In which of the following Knowledge Areas are you working?

  • A Project Integration Management
  • B Project Time Management
  • C Project Scope Management
  • D Project Risk Management
Explanation

Developing a project schedule requires analyzing activity sequencing, duration estimates, resource requirements, and schedule constraints. In the terminology represented by these choices, this work belongs to Project Time Management.