QuestionQ193

Managing Projects

You are working within a functional organization and managing the IHH Project. The project will likely run for six months and has a budget constraint of $1,876,000. You will work with a functional manager to manage project costs and resources. Who has authority to assign project team members to activities?

  • A Customers
  • B Project sponsor
  • C Functional manager
  • D Team leader
Explanation

In a functional organization, the functional manager controls departmental personnel and has the authority to allocate staff and assign them to project activities. The project manager’s authority over resources is limited.