QuestionQ193
Managing ProjectsYou are working within a functional organization and managing the IHH Project. The project will likely run for six months and has a budget constraint of $1,876,000. You will work with a functional manager to manage project costs and resources. Who has authority to assign project team members to activities?
- A Customers
- B Project sponsor
- C Functional manager
- D Team leader