QuestionQ187
Managing ProjectsYou are developing the change management plan for an upcoming project and want to address mistakes that might occur while the project is being executed.
Your change management plan requires the project team to correct any errors that deviate from the project scope, because an error is technically an unapproved scope change. What else should you address regarding errors in project team execution?
- A The schedule delays of the error must be documented.
- B The corrective action for the errors must be followed by validating defect repair.
- C The corrective action for the errors must be followed by quality control.
- D The costs of the error must be documented.